Oregon Statutes

§ 543.410 — Construction of project; time for commencement and completion; supply of service; extension of time; nonperformance; termination of license

Oregon § 543.410
JurisdictionOregon
Vol.15
Title 45Water Resources; Irrigation, Drainage, Flood Control, Reclamation
Ch. 543Hydroelectric Projects

This text of Oregon § 543.410 (Construction of project; time for commencement and completion; supply of service; extension of time; nonperformance; termination of license) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Or. Rev. Stat. § 543.410 (2026).

Text

(1)The licensee shall commence the construction of the project works within the time fixed in the license, which shall not be more than two years from the date thereof, shall thereafter in good faith and with due diligence prosecute such construction, and shall, within the time fixed in the license, complete and put into operation such part of the ultimate development as the Water Resources Commission considers necessary to supply the reasonable needs of the then available market, and shall, from time to time thereafter construct such portion of the balance of the development as the commission directs, so as to supply adequately the reasonable market demands until development is completed.
(2)The period for commencement of construction may be extended once but not longer than two additio

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Amended by 1985 c.673 §155