Oregon Statutes

§ 540.461 — Plan and time frame for corrective action; hearing; proposed and final orders

Oregon § 540.461
JurisdictionOregon
Vol.15
Title 45Water Resources; Irrigation, Drainage, Flood Control, Reclamation
Ch. 540Distribution and Storage of Water; Watermasters; Water Right Changes,

This text of Oregon § 540.461 (Plan and time frame for corrective action; hearing; proposed and final orders) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Or. Rev. Stat. § 540.461 (2026).

Text

(1)If the Water Resources Department provides notification to a dam owner under ORS 540.458 stating that the department has concluded that a dam having a significant hazard rating or high hazard rating is unsafe or potentially unsafe, the department may cooperate with dam owner efforts to develop a plan and time frame for corrective action that is agreeable to the department. When determining whether a plan and time frame for corrective action developed by a dam owner is agreeable to the department, the department may consider any relevant information, including, but not limited to, information regarding:
(a)The specific dam;
(b)The efforts and resources of the dam owner; and
(c)The impacts associated with dam failure.
(2)In addition to any other available remedies, the Water Resource

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 540.458
Oregon § 540.458
§ 183.413
Oregon § 183.413

Legislative History

2019 c.390 §8

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Oregon § 540.461, Counsel Stack Legal Research, https://law.counselstack.com/statute/or/540.461.