This text of Oregon § 537.248 (Requirement to include in reservoir permit date for beginning and completing construction and for perfecting water right; extension) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Or. Rev. Stat. § 537.248 (2026).

Text

(1)When the Water Resources Department issues a reservoir permit for a new storage project to a county, municipality or district, the department shall include in the permit a date, not more than 10 years after the date the permit is issued, to begin and complete construction of diversion or storage works and to perfect the water right. An application for a reservoir permit under this section shall be subject to the provisions of ORS 537.140 to 537.211, except that the applicant need not submit engineering plans and specifications before the permit is issued. However, the applicant may not begin construction of the reservoir until the department approves the engineering plans and specifications.
(2)By order, the Water Resources Director may extend the date for beginning and completing con

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 537.140
Oregon § 537.140
§ 198.010
Oregon § 198.010

Legislative History

1995 c.473 §2; 1995 c.416 §35a

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Oregon § 537.248, Counsel Stack Legal Research, https://law.counselstack.com/statute/or/537.248.