§ 517.820 — Extensions of time for submission of proposed reclamation plans; time limit for reclamation completion; consultation with cooperating agencies

Oregon § 517.820
JurisdictionOregon
Vol.14
Title 43Mineral Resources
Ch. 517Mining and Mining Claims

This text of Oregon § 517.820 (Extensions of time for submission of proposed reclamation plans; time limit for reclamation completion; consultation with cooperating agencies) is published on Counsel Stack Legal Research, covering Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Or. Rev. Stat. § 517.820 (2026).

Text

(1)Upon good cause shown, the State Department of Geology and Mineral Industries may grant reasonable extensions of time for the completion by the landowner or operator and the submission to the department of a proposed reclamation plan required by ORS 517.790. Each reclamation plan submitted to the department must provide that all reclamation activities shall be completed within three years after the termination of mineral extraction from the surface mining operation conducted within each separate area for which an operating permit is requested. Each such reclamation plan shall be approved by the department if it adequately provides for the reclamation of surface-mined lands.
(2)Prior to approving a proposed reclamation plan, the department shall consult with all other cooperating agenc

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 517.790
Oregon § 517.790

Legislative History

1971 c.719 §5; 1977 c.59 §2; 2007 c.318 §17; 2017 c.736 §4