§ 61-225 — Suspension or termination of construction contract -

Oklahoma § 61-225
JurisdictionOklahoma
Title 61Public Buildings And Public Works

This text of Oklahoma § 61-225 (Suspension or termination of construction contract -) is published on Counsel Stack Legal Research, covering Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Okla. Stat. tit. 61, § 61-225 (2026).

Text

Payment.

A.Any prime contractor that performs work under a construction contract may suspend performance of the work or may terminate a construction contract if the prime contractor is not properly paid within forty-nine (49) calendar days of the date that the corresponding proper invoice is submitted. Written notice must be received by the owner at least seven (7) calendar days before any such intended suspension or termination.
B.A prime contractor or any entity that suspends performance due to the suspension of a prime contractor, is not required to furnish further performance until such entity is paid for the full amount, less retainage, of work performed, material supplied, or services rendered, together with any costs incurred for demobilization, mobilization and other costs attrib

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Added by Laws 2004, c. 256, § 5, eff. Nov. 1, 2004. Amended by Laws 2004, c. 425, § 4, eff. July 1, 2004; Laws 2005, c. 92, § 3, eff. Nov. 1, 2005. Renumbered from Title 15, § 625 by Laws 2005, c. 92, § 6, eff. Nov. 1, 2005.