§ 61-223 — Construction contracts - Progress payments - Reduction.

Oklahoma § 61-223
JurisdictionOklahoma
Title 61Public Buildings And Public Works

This text of Oklahoma § 61-223 (Construction contracts - Progress payments - Reduction.) is published on Counsel Stack Legal Research, covering Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Okla. Stat. tit. 61, § 61-223 (2026).

Text

A.On all construction contracts exceeding Twenty-five Thousand Dollars ($25,000.00) in value an owner shall make progress payments to the prime contractor for work performed and materials properly stored, within thirty (30) calendar days after a proper invoice is submitted to the owner or a representative designated by the owner.
B.An owner or entity designated by the owner, may not reduce a proper invoice of a prime contractor without detailing and forwarding to the prime contractor, within fourteen (14) calendar days of receipt of the proper invoice, the reasons for reduction. The reduction may not be more than an amount that is reasonable to correct the work, as set forth in writing.
C.If a contracting entity has had their proper invoice reduced by another entity all other affected e

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Added by Laws 2004, c. 256, § 3, eff. Nov. 1, 2004. Amended by Laws 2004, c. 425, § 3, eff. July 1, 2004; Laws 2005, c. 92, § 2, eff. Nov. 1, 2005. Renumbered from Title 15, § 623 by Laws 2005, c. 92, § 6, eff. Nov. 1, 2005.