§ 61-121 — Change orders or addenda.

Oklahoma·Title 61 Public Buildings And Public Works
A.Change orders or addenda to public construction contracts of One Million Dollars ($1,000,000.00) or less shall not exceed a fifteen percent (15%) cumulative increase in the original contract amount.
B.Change orders or addenda to public construction contracts of over One Million Dollars ($1,000,000.00) shall not exceed the greater of One Hundred Fifty Thousand Dollars ($150,000.00) or a ten percent (10%) cumulative increase in the original contract amount.
C.Change orders or cumulative change orders which exceed the limits of subsection A or B of this section shall require a readvertising for bids on the incomplete portions of the contract.
D.If the awarding public agency does not have a governing body, the chief administrative officer of the awarding public agency shall approve chang

Free access — add to your briefcase to read the full text and ask questions with AI

Oklahoma § 61-121 (Change orders or addenda.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Added by Laws 1974, c. 298, § 21, operative Aug. 1, 1974. Amended by Laws 1975, c. 266, § 9, emerg. eff. June 5, 1975; Laws 1989, c. 164, § 1, emerg. eff. May 8, 1989; Laws 1993, c. 293, § 2, emerg. eff. June 3, 1993; Laws 1995, c. 200, § 3, emerg. eff. May 19, 1995; Laws 1997, c. 72, § 1, eff. Nov. 1, 1997; Laws 1998, c. 118, § 1, eff. July 1, 1998; Laws 2000, c. 363, § 11, emerg. eff. June 6, 2000; Laws 2002, c. 294, § 22, eff. Nov. 1, 2002; Laws 2004, c. 328, § 2, eff. July 1, 2004; Laws 2006, c. 271, § 23, eff. July 1, 2006; Laws 2009, c. 257, § 3, eff. Nov. 1, 2009; Laws 2011, c. 112, § 1, eff. Nov. 1, 2011; Laws 2012, c. 304, § 315; Laws 2013, c. 170, § 1, eff. Nov. 1, 2013; Laws 2017, c. 68, § 1, eff. Nov. 1, 2017; Laws 2019, c. 299, § 4, eff. Jan. 1, 2020; Laws 2022, c. 238, § 26, eff. Nov. 1, 2022.