§ 6131.45 — Extending the contract time

Ohio § 6131.45
JurisdictionOhio
Title 61Water Supply-Sanitation-Ditches
Ch. 6131Single County Drainage Improvements

This text of Ohio § 6131.45 (Extending the contract time) is published on Counsel Stack Legal Research, covering Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Rev. Code Ann. § 6131.45 (2026).

Text

The time fixed in a contract for the performance of any work or the furnishing of any material, on good cause shown by affidavit, may be extended by the board of county commissioners with the approval of the county engineer for any definite period that it finds is reasonably necessary to complete the work or furnish the material under the contract. In case of such extensions the contractor's bond and any sureties thereon shall remain liable as if the extended time had been originally named in the bond or contract. The board shall not extend the contract time of furnishing any material to be used by a contractor unless by consent of the contractor the time for performance of his contract is correspondingly extended. Any order extending or refusing to extend the contract time shall be by re

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Effective: April 9, 1981 | Latest Legislation: House Bill 268 - 113th General Assembly