Ohio Statutes

§ 5555.66 — Payment on estimates of materials delivered shall not exceed ninety per cent

Ohio § 5555.66
JurisdictionOhio
Title 55Roads-Highways-Bridges
Ch. 5555County Road Improvement

This text of Ohio § 5555.66 (Payment on estimates of materials delivered shall not exceed ninety per cent) is published on Counsel Stack Legal Research, covering Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Rev. Code Ann. § 5555.66 (2026).

Text

In addition to the estimates provided for by section153.13of the Revised Code, the county engineer may, under such conditions as he prescribes, allow and pay to a contractor a sum not exceeding ninety per cent of the value of material delivered by such contractor, and safely stored at a railroad station or siding or other point in the vicinity of the work. When such estimate is allowed, the material on which it is allowed shall thereupon become the property of the county, but in case such material is stolen, destroyed, or damaged by casualty before being used, or for any reason becomes unfit for use, the contractor shall replace it at his own expense. A contractor may insure against loss or damage, by fire or otherwise, all materials upon which estimates have been allowed under this or any

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Effective: August 27, 1976 | Latest Legislation: Senate Bill 330 - 111th General Assembly

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Ohio § 5555.66, Counsel Stack Legal Research, https://law.counselstack.com/statute/oh/5555.66.