This text of Nevada § 704.797 (Requirements for energy storage systems procured to meet targets) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nev. Rev. Stat. § 704.797 (2026).

Text

1. If the Commission adopts regulations pursuant to NRS 704.796 to establish biennial targets for the procurement of energy storage systems by an electric utility, to meet the targets set forth in those regulations, the electric utility may procure energy storage systems that are either centralized or distributed and either owned by the utility or by any other person, as prescribed by regulation of the Commission. 2. Electric energy storage systems procured by an electric utility to meet any biennial targets for the procurement of energy storage systems established by regulation pursuant to NRS 704.796 must:

(a)Reduce peak demand for electricity;
(b)Avoid or defer investment by the electric utility in assets for the generation, transmission and distribution of electricity;
(c)Improve th

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 704.796
Nevada § 704.796

Legislative History

(Added to NRS by 2017, 1274 )