Nevada Statutes

§ 704.711 — Decision on application for adjustment; conditions; requirements for approval; federal or state grants

Nevada § 704.711
JurisdictionNevada
Title 58ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES
Ch. 704Regulation
Conversion of Certain Generation Facilities

This text of Nevada § 704.711 (Decision on application for adjustment; conditions; requirements for approval; federal or state grants) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nev. Rev. Stat. § 704.711 (2026).

Text

1. The Commission shall render its written decision within 180 days after receiving the application for such an adjustment. 2. The Commission shall render its decision based on the record and may grant the application, deny it or grant it according to such terms, conditions or modifications as the Commission finds appropriate. 3. The Commission may grant an application for such an adjustment if it determines that:

(a)There is substantial evidence that the projected saving in fuel is greater than the cost of conversion.
(b)The conversion is consistent with and included in the utility’s plan for resources.
(c)The conversion will substantially benefit the utility’s customers. 4. If the applicant becomes, by reason of the conversion, entitled to any federal or state grant, the Commission sh

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(Added to NRS by 1983, 752 )

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Nevada § 704.711, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/704.711.