Nevada Statutes
§ 445D.180 — Duration; amendment by court action
Nevada § 445D.180
This text of Nevada § 445D.180 (Duration; amendment by court action) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Nev. Rev. Stat. § 445D.180 (2026).
Text
1. An environmental covenant is perpetual unless it is:
(a)By its terms limited to a specific duration or terminated by the occurrence of a specific event;
(b)Terminated by consent pursuant to NRS 445D.190 ;
(c)Terminated pursuant to subsection 2;
(d)Terminated by foreclosure of an interest that has priority over the environmental covenant; or
(e)Terminated or modified in an eminent domain proceeding, but only if:
(1)The agency that signed the covenant is a party to the proceeding;
(2)All persons identified in subsections 1 and 2 of NRS 445D.190 are given notice of the pendency of the proceeding; and
(3)The court determines, after hearing, that the termination or modification will not adversely affect human health or the environment.
2. If the agency that signed an environmental co
Free access — add to your briefcase to read the full text and ask questions with AI
Related
§ 445D.190
Nevada § 445D.190
§ 233B.130
Nevada § 233B.130
Legislative History
(Added to NRS by 2005, 1365 )
Nearby Sections
15
§ 445D.010
Short title§ 445D.020
Definitions§ 445D.030
“Activity and use limitations” defined§ 445D.040
“Agency” defined§ 445D.050
“Common-interest community” defined§ 445D.060
“Environmental covenant” defined§ 445D.070
“Environmental response project” defined§ 445D.080
“Holder” defined§ 445D.090
“Person” defined§ 445D.100
“Record” defined§ 445D.110
“State” defined§ 445D.130
Contents§ 445D.140
Validity; effect on other instruments§ 445D.150
Relationship to other land-use lawCite This Page — Counsel Stack
Bluebook (online)
Nevada § 445D.180, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/445D.180.