§ 408.346 — Monetary incentive for early completion of contract
Nevada § 408.346
JurisdictionNevada
Title 35HIGHWAYS; ROADS; BRIDGES; PARKS; OUTDOOR
Ch. 408Highways,
General Provisions
This text of Nevada § 408.346 (Monetary incentive for early completion of contract) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Nev. Rev. Stat. § 408.346 (2026).
Text
1.Any contract made or awarded by the Department for the construction, improvement, maintenance or repair of a highway or an appurtenance to that highway may include a provision for the payment of an additional amount of money to the person with whom the contract is made or to whom it is awarded if the person satisfactorily completes the construction, improvement, maintenance or repair of the highway or appurtenance before the date for completion of that construction, improvement, maintenance or repair set forth in the contract.
2.The amount of money to be paid pursuant to a provision included in a contract specified in subsection 1 and the date before which the work must be completed must be determined by the Department.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
(Added to NRS by 1999, 1652 )
Nearby Sections
15
§ 408.010
Short title§ 408.015
Rules of construction§ 408.020
Definitions§ 408.033
“Board” defined§ 408.037
“Business” defined§ 408.040
“City” defined§ 408.042
“Conveyance system” defined§ 408.045
“Department” defined§ 408.046
“Director” defined§ 408.0465
“Discharge” defined§ 408.047
“Displaced person” defined§ 408.050
“Encroachment” defined§ 408.056
“Family” defined§ 408.057
“Farm operation” defined§ 408.058
“Farmer” definedCite This Page — Counsel Stack
Bluebook (online)
Nevada § 408.346, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/408.346.