§ 40.646 — Notice of defect to be forwarded by contractor to subcontractor, supplier or design professional; effect of failure to forward notice; inspection of alleged defect; election to repair
Nevada·Title 3 REMEDIES; SPECIAL ACTIONS AND PROCEEDINGS·Ch. 40 Actions· Conditions and Limitations on Actions
1.Except as otherwise provided in subsection 2, not later than 30 days after the date on which a contractor receives notice of a constructional defect pursuant to NRS 40.645 , the contractor shall forward a copy of the notice by certified mail, return receipt requested, to the last known address of each subcontractor, supplier or design professional whom the contractor reasonably believes is responsible for a defect specified in the notice.
2.If a contractor does not provide notice as required pursuant to subsection 1, the contractor may not commence an action against the subcontractor, supplier or design professional related to the constructional defect unless the contractor demonstrates that, after making a good faith effort, the contractor was unable to identify the subcontractor, sup
Free access — add to your briefcase to read the full text and ask questions with AI
Nevada § 40.646 (Notice of defect to be forwarded by contractor to subcontractor, supplier or design professional; effect of failure to forward notice; inspection of alleged defect; election to repair) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Shuette v. Beazer Homes Holdings Corp.
124 P.3d 530 (Nevada Supreme Court, 2005)
Barrett v. Eighth Jud. Dist. Ct.
2014 NV 65 (Nevada Supreme Court, 2014)
Pulver v. Kane
(D. Nevada, 2022)
Legislative History
(Added to NRS by 2003, 2035 ; A 2015, 11 )
Nearby Sections
15
§ 40.001
Definitions§ 40.002
“Federal worker” defined§ 40.0025
“Household member” defined§ 40.003
“Qualified Indian tribe” defined§ 40.0035
“Shutdown” defined§ 40.004
“State worker” defined§ 40.0045
“Tribal worker” defined§ 40.050
Mortgage not deemed conveyance