§ 278.566 — Written report of construction committee required before building official may issue building permit; application for written report; exceptions

Nevada § 278.566
JurisdictionNevada
Title 22COOPERATIVE AGREEMENTS BY PUBLIC AGENCIES; REGIONAL
Ch. 278Planning
Deed Restrictions for Subdivisions in Unincorporated Areas of Certain Counties

This text of Nevada § 278.566 (Written report of construction committee required before building official may issue building permit; application for written report; exceptions) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nev. Rev. Stat. § 278.566 (2026).

Text

1.Except as provided in subsection 3, the building official in a county whose population is 100,000 or more but less than 700,000, shall not issue any building permit for the construction, reconstruction, alteration or use of any building or other structure on a lot subject to deed restrictions unless the building official has received a written report thereon from the construction committee.
2.An application for a written report must be made by certified mail addressed to the authorized representative of the construction committee. If the construction committee fails or refuses to submit its written report to the building official within 20 days from the date of its receipt of a written request therefor, the building official must proceed as provided by law in cases where there is no fu

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(Added to NRS by 1973, 1725 ; A 1979, 531 ; 1989, 1918 ; 2001, 1247 ; 2011, 1201 )