§ 278.02073 — Building permit for residential or commercial project: Extension of period of validity when financing is not available and land is leased for renewable energy generation project

Nevada § 278.02073
JurisdictionNevada
Title 22COOPERATIVE AGREEMENTS BY PUBLIC AGENCIES; REGIONAL
Ch. 278Planning
GENERAL PROVISIONS

This text of Nevada § 278.02073 (Building permit for residential or commercial project: Extension of period of validity when financing is not available and land is leased for renewable energy generation project) is published on Counsel Stack Legal Research, covering Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nev. Rev. Stat. § 278.02073 (2026).

Text

1. A director of planning or a governing body may extend the period for which a building permit for a residential or commercial project is valid if the person to whom the permit has been issued:

(a)Applies for an extension before July 1, 2013, subject to any applicable ordinances or regulations adopted by the governing body;
(b)Demonstrates to the satisfaction of the director of planning or governing body that:
(1)Financing for the residential or commercial project is not available; and
(2)The land will be leased for a renewable energy generation project; and
(c)Submits with his or her application for an extension an affidavit showing that due diligence has been used to obtain financing for the residential or commercial project. The affidavit must include, without limitation, evidence

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(Added to NRS by 2009, 2280 )