“Utility project” means:

1.An electric transmission line which is designed to operate at 200 kilovolts or more; or
2.A line used to transport natural gas which operates at 20 percent or more of the specified minimum yield strength of the material from which the line is constructed, Ê which has been approved for construction after October 1, 1991, by the State or Federal Government or a governing body.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(Added to NRS by 1993, 2558 )

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Nevada § 278.0195, Counsel Stack Legal Research, https://law.counselstack.com/statute/nv/278.0195.