New Mexico Statutes

§ 69-36-11 — Existing mining operations; closeout plan required

New Mexico § 69-36-11
JurisdictionNew Mexico
Ch. 69Mines
Art. 36Mining

This text of New Mexico § 69-36-11 (Existing mining operations; closeout plan required) is published on Counsel Stack Legal Research, covering New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.M. Stat. Ann. § 69-36-11 (2026).

Text

A.An owner or operator of an existing mining operation shall submit a permit application to the director by December 31, 1994. The permit application shall contain all information required by regulation of the commission, including a proposed compliance schedule for submission of a closeout plan within the shortest time practicable. The director shall approve or deny the permit application within six months after it has been deemed complete.
B.The owner or operator of an existing mining operation shall submit a closeout plan in accordance with the compliance schedule in the permit. The compliance schedule in the permit shall require submission of a closeout plan by December 31, 1995 unless the operator shows good cause for a further extension of time. The director shall approve a modific

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Laws 1993, ch. 315, § 11.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
New Mexico § 69-36-11, Counsel Stack Legal Research, https://law.counselstack.com/statute/nm/69/69-36-11.