§ 40A:11-19 — Liquidated damages; void provisions as to contractor's remedies
New Jersey·Title 40A MUNICIPALITIES AND COUNTIES
19.Any contract made pursuant to P.L.1971, c.198 (C.40A:11-1 et seq.) may include liquidated damages for the violation of any of the terms and conditions thereof or the failure to perform said contract in accordance with its terms and conditions, or the terms and conditions of P.L.1971, c.198 (C.40A:11-1 et seq.). Notwithstanding any other provision of law to the contrary, it shall be void, unenforceable and against public policy for a provision in a contract entered into under P.L.1971, c.198 (C.40A:11-1 et seq.) to limit a contractor's remedy for the contracting unit's negligence, bad faith, active interference, tortious conduct, or other reasons uncontemplated by the parties that delay the contractor's performance, to giving the contractor an extension of time for performance under the
Free access — add to your briefcase to read the full text and ask questions with AI
New Jersey § 40A:11-19 (Liquidated damages; void provisions as to contractor's remedies) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
15
§ 40A:11-1
Short title; citation§ 40A:11-11
Additional matters regarding contracts for the provision and performance of goods and services.§ 40A:11-13
Specifications.§ 40A:11-13.1
Payment from bequest, legacy or gift; conditions.§ 40A:11-13.2
Rejection of bids; reasons.§ 40A:11-13a
Contracts, low-volume road, reclaimed asphalt pavement, maximum percentage, total pavement mixtures.§ 40A:11-14
Form of contracts.§ 40A:11-15
Duration of certain contracts.§ 40A:11-15.1. Insurance contract to fund actuarial liability
§ 40A:11-15.1. Insurance contract to fund actuarial liability§ 40A:11-15.3
Contract for marketing of recyclable materials.§ 40A:11-16
Separate plans, specifications; contracts.