New Hampshire Statutes
§ 482:32 — Effect of Finding
New Hampshire § 482:32
JurisdictionNew Hampshire
Title LWATER MANAGEMENT AND PROTECTION
Ch. 482DAMS, MILLS, AND FLOWAGE
SubdivisionProceedings Before the Department
This text of New Hampshire § 482:32 (Effect of Finding) is published on Counsel Stack Legal Research, covering New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
N.H. Rev. Stat. Ann. § 482:32 (2026).
Text
No other dam shall be erected to the injury of any proposed dam or any proposed increase in any existing dam which, in either case, has been found to be for the public good by the department pursuant to this subdivision, if the petitioner shall, within 3 years after such finding or within such further time as the department for good cause may grant, commence the construction and prosecute said construction with reasonable diligence.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
1989, 339:1. 1996, 228:106, eff. July 1, 1996.
Nearby Sections
15
§ 482:1
Purpose§ 482:10
Supervision§ 482:11
Orders§ 482:11-a
Duty of Owner§ 482:12-a
Emergency Actions§ 482:12-b
Rights of Entry and Access§ 482:14
Appeals§ 482:16
Expenses§ 482:17
Right Granted§ 482:18
Conflicting Claims§ 482:2
DefinitionsCite This Page — Counsel Stack
Bluebook (online)
New Hampshire § 482:32, Counsel Stack Legal Research, https://law.counselstack.com/statute/nh/482/482%3A32.