This text of Nebraska § 57-1619 (Certificate of project completion; notice; hearing; consultation; issuance; conditions; effect) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neb. Rev. Stat. § 57-1619 (2026).

Text

(1)After carbon dioxide injections into a reservoir end and upon application by the storage operator, the commission shall consider issuing a certificate of project completion.
(2)The certificate may only be issued after public notice and hearing. The commission shall establish notice requirements for such hearing.
(3)The certificate may only be issued after the commission has consulted with the Department of Water, Energy, and Environment and the Underground Injection Control program permitting authority.
(4)The certificate may only be issued if the storage operator:
(a)Is in full compliance with all laws governing the storage facility;
(b)Shows that it has addressed all pending claims regarding the storage facility's operation;
(c)Shows that it has received an authorization of sit

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Source: Laws 2021, LB650, § 19; Laws 2025, LB317, § 320. Operative Date: July 1, 2025