Nebraska Statutes
§ 52-143 — Obligation of claimant to furnish information to other lien claimant; damages; applicability of section
Nebraska § 52-143
JurisdictionNebraska
Ch. 52Liens
This text of Nebraska § 52-143 (Obligation of claimant to furnish information to other lien claimant; damages; applicability of section) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Neb. Rev. Stat. § 52-143 (2026).
Text
(1)A prime contractor, on request, is obligated to furnish the following information within a reasonable time, not exceeding ten days, to any person entitled to claim a lien through him or her:
(a)A description of the real estate being improved sufficient to identify it;
(b)The name and address of the contracting owner with whom the prime contractor contracted; and
(c)Whether there is a surety bond and, if so, the name of the surety.
(2)At the request of any person who may claim a lien through him or her, any claimant other than a prime contractor must furnish, within a reasonable time not exceeding five days, the name of the person who contracted for the furnishing by the claimant of the materials or services in connection with which the lien claim may arise.
(3)A person who fails t
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Source: Laws 1981, LB 512, § 19.
Nearby Sections
15
§ 52-1001
Federal liens; notice; filing§ 52-1002
Certifications; filing§ 52-1004
Notice; filing; fees; billing§ 52-1006
Act, how construed§ 52-1007
Act, how citedCite This Page — Counsel Stack
Bluebook (online)
Nebraska § 52-143, Counsel Stack Legal Research, https://law.counselstack.com/statute/ne/52-143.