§ 37-1729 — Commission; duties; powers

Nebraska § 37-1729
JurisdictionNebraska
Ch. 37Game and Parks

This text of Nebraska § 37-1729 (Commission; duties; powers) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neb. Rev. Stat. § 37-1729 (2026).

Text

(1)Before the construction manager begins any construction services, the commission shall:
(a)Conduct an independent cost estimate for the project; and
(b)Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.
(2)If the construction manager and the commission are unable to negotiate a contract, the commission may use other contract procurement processes as provided by law. Persons or organizations who submitted proposals but were unable to negotiate a contract with the commission shall be eligible to compete in the other contract procurement processes.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Source: Laws 2018, LB775, § 30.