This text of Nebraska § 31-912 (Proposed drainage improvement plan; county board; proceed with plan) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Neb. Rev. Stat. § 31-912 (2026).
Text
In the event no appeal is perfected as provided in section 31-911 , or upon final determination of said appeal, unless the court should hold that the improvement is not conducive to public health, convenience and welfare, the board shall proceed as follows:
(1)If the estimated cost of the improvement is two thousand dollars, or less, the board may, through rental of equipment or private contract, make said improvements without public letting;
(2)If the estimated cost of the improvement is more than two thousand dollars, plans and specifications therefor shall be drawn by an engineer employed by said board. At such time as the plans and specifications are complete, the board shall fix a time for the opening of bids on said improvement and publish notice thereof for three weeks prior to s
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Source: Laws 1959, c. 132, § 12, p. 488.
Nearby Sections
15
§ 31-1002
Definitions, where found§ 31-1003
Department, defined§ 31-1004
Repealed. Laws 1993, LB 626, § 8§ 31-1005
Base flood, defined§ 31-1006
Drainway, defined§ 31-1007
Flood, defined§ 31-1008
Floodway, defined§ 31-1009
Flood fringe, defined§ 31-1010
Flood plain, defined§ 31-1011
Flood plain management, defined§ 31-1013
Local government, definedCite This Page — Counsel Stack
Bluebook (online)
Nebraska § 31-912, Counsel Stack Legal Research, https://law.counselstack.com/statute/ne/31-912.