§ 13-2912 — Contracts; refinements; changes authorized

Nebraska·Ch. 13 Cities, Counties, and Other Political Subdivisions
A design-build contract and a construction management at risk contract may be conditioned upon later refinements in scope and price and may permit the political subdivision in agreement with the design-builder or construction manager to make changes in the project without invalidating the contract. Later refinements under this section shall not exceed the scope of the project statement contained in the request for proposals pursuant to section 13-2907 or 13-2909 .

Free access — add to your briefcase to read the full text and ask questions with AI

Nebraska § 13-2912 (Contracts; refinements; changes authorized) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Source: Laws 2002, LB 391, § 12; R.S.1943, (2003), § 79-2012; Laws 2008, LB889, § 12.