Text
The contractor's bond must be made payable to the district and must be conditioned:
1.That the contractor well and faithfully will perform the work bid for in accordance with
the terms of and within the time provided for in the contract, and pursuant to the plans
and specifications for the work on file in the district office;
2.That the contractor will pay for all labor and material used in that work; and
3.That in case of a default on the part of the bidder or contractor in the performance of
the work as provided in the contract, the sum named in the bond must be taken and
held to cover the amount necessary to compensate the district for the correction,
repair, or replacement caused by the default, and that the full amount may be
recovered from the bidder and the bidder's sureties in
Free access — add to your briefcase to read the full text and ask questions with AI
Nearby Sections
15
§ 61-01-01
Waters of the state - Public waters§ 61-01-01.1
Reciprocal rights of riparian owners§ 61-01-02
Right to use water - Basis - Waters appropriated for irrigation purposes - Priority in time§ 61-01-04
Eminent domain - Who may exercise§ 61-01-06
Watercourse and waterway - Definitions§ 61-01-07
Obstruction of watercourses - Penalty§ 61-01-08
Obstructing navigation - Penalty§ 61-01-09
Destruction of dams - Penalty§ 61-01-11
Removing or injuring piles - PenaltyCite This Page — Counsel Stack
Bluebook (online)
North Dakota § 61-35-97, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/61-35-97.