North Dakota Statutes
§ 35-27-22 — Order of priority of classes of construction liens
1.Liens perfected under this chapter have priority in the following order:
a.For manual labor.
b.For materials.
c.Subcontractors other than manual laborers.
d.Original contractors.
2.Liens for manual labor filed within the ninety-day period must share ratably in the
security. Liens for manual labor filed after the ninety-day period have priority in the
order of the filing of such liens. Liens for materials filed within the ninety-day period
must share ratably in the security and liens filed after the ninety-day period have
priority in the order of the filing of such liens.
Free access — add to your briefcase to read the full text and ask questions with AI
North Dakota § 35-27-22 (Order of priority of classes of construction liens) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Nearby Sections
15
§ 35-01-01
Scope of statutes relating to liens§ 35-01-02
Definition of lien§ 35-01-05.1
When security interest in vehicle valid§ 35-01-05.2
Priority of liens securing future advances§ 35-01-06
Obligations not in existence§ 35-01-08
Lien transfers no title§ 35-01-09
Recorder to file and index lien