This text of North Dakota § 35-27-22 (Order of priority of classes of construction liens) is published on Counsel Stack Legal Research, covering North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.D. Cent. Code § 35-27-22 (2026).

Text

1.Liens perfected under this chapter have priority in the following order:
a.For manual labor.
b.For materials.
c.Subcontractors other than manual laborers.
d.Original contractors.
2.Liens for manual labor filed within the ninety-day period must share ratably in the security. Liens for manual labor filed after the ninety-day period have priority in the order of the filing of such liens. Liens for materials filed within the ninety-day period must share ratably in the security and liens filed after the ninety-day period have priority in the order of the filing of such liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
North Dakota § 35-27-22, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/35-27-22.