North Carolina Statutes

§ 87-122 — Excavator responsibilities

North Carolina·Ch. 87 Contractors·Art. 8A Underground Utility Safety and Damage Prevention Act
(a)Before commencing any excavation or demolition operation, the person responsible for the excavation or demolition shall provide or cause to be provided notice to the Notification Center of his or her intent to excavate or demolish. Notice for any excavation or demolition that does not involve a subaqueous facility must be given within three to 12 full working days before the proposed commencement date of the excavation or demolition. Notice for any excavation or demolition in the vicinity of a subaqueous facility must be given within 10 to 20 full working days before the proposed commencement date of the excavation or demolition. Notice given pursuant to this subsection shall expire 15 full working days after the date notice was given. No excavation or demolition may continue after thi

Free access — add to your briefcase to read the full text and ask questions with AI

North Carolina § 87-122 (Excavator responsibilities) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

§ 195.2
49 C.F.R. § 195.2
§ 192.3
49 C.F.R. § 192.3

Nearby Sections

15