§ 69-8-421 — Approval Of Electricity Supply Resources

Montana § 69-8-421
JurisdictionMontana
Title 69PUBLIC UTILITIES AND CARRIERS
Ch. 8ELECTRIC UTILITY INDUSTRY GENERATION REINTEGRATION
Part 4Public Utilities, Cooperative Utilities, and Electricity Suppliers

This text of Montana § 69-8-421 (Approval Of Electricity Supply Resources) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mont. Code Ann. § 69-8-421 (2026).

Text

69-8-421 . Approval of electricity supply resources.

(1)A public utility may apply to the commission for approval of an electricity supply resource that:
(a)is not yet procured; and
(b)is subject to a competitive solicitation process when applicable in accordance with 69-3-1207 .
(2)Within 45 days of the public utility's submission of an application for approval, the commission shall determine whether or not the application is adequate and in compliance with the commission's minimum filing requirements. If the commission determines that the application is inadequate, it shall explain the deficiencies.
(3)The commission shall issue an order within 180 days of receipt of an adequate application for approval of a power purchase agreement from an existing generating resource unless it det

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 3, Ch. 509, L. 2003; amd. Sec. 15, Ch. 491, L. 2007; amd. Sec. 94, Ch. 2, L. 2009; amd. Sec. 15, Ch. 449, L. 2019; amd. Sec. 2, Ch. 251, L. 2023; amd. Sec. 7, Ch. 632, L. 2025.