§ 90-4-1221 — Requirements Prior To Project Construction
Montana·Title 90 PLANNING, RESEARCH, AND DEVELOPMENT·Ch. 4 ENERGY DEVELOPMENT AND CONSERVATION·Part 12 Montana Clean Renewable Energy Bond Act
90-4-1221 . Requirements prior to project construction. Prior to starting construction under this part, the governmental body shall enter into a contract or contracts:
(1)with a transmission services provider to interconnect with the transmission or distribution facilities of a utility or cooperative;
(2)that ensure that all ancillary services as required by the control area operator are available to regulate the generation of electricity from the project;
(3)for the sale of electricity from the project; and
(4)with a tribal government for projects being constructed within the exterior boundaries of that tribal government's Indian reservation.
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 90-4-1221 (Requirements Prior To Project Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 16, Ch. 378, L. 2007.
Nearby Sections
15
§ 90-4-1001
Repealed§ 90-4-1002
Repealed§ 90-4-1003
Repealed§ 90-4-1004
Terminated§ 90-4-1006
Through 90-4-1009 Reserved§ 90-4-101
Repealed§ 90-4-1010
Transportation Energy Policy§ 90-4-102
Repealed§ 90-4-103
Repealed§ 90-4-104
Repealed§ 90-4-105
Repealed§ 90-4-106
Repealed§ 90-4-107
Renumbered 90-4-111