82-4-439 . Extended review -- criteria -- timeframes.

(1)The department may subject an opencut application to an extended review if the department determines that comments received at a public meeting held pursuant to 82-4-432 reveal the proposed plan of operation violates provisions of this part.
(2)(a) For a complete application subject to an extended review, the department shall, within 60 days from the date the department determines the application warrants an extended review, inspect the proposed site if the department determines an inspection is necessary and notify the applicant as to whether or not the application is acceptable pursuant to 82-4-432 . If the application is unacceptable, the notice must include a detailed explanation of the deficiencies.
(b)Within 30 days of recei

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 8, Ch. 477, L. 2009; amd. Sec. 6, Ch. 545, L. 2021.