Text
82-4-352 . Reapplication with new reclamation plan. A permit may be denied and returned to the applicant with a request that the application be resubmitted with a different plan for reclamation. The person making application for a permit may then resubmit to the department a new plan for reclamation.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
En. Sec. 15, Ch. 252, L. 1971; R.C.M. 1947, 50-1215; amd. Sec. 399, Ch. 418, L. 1995.
Nearby Sections
15
§ 82-4-1001
Penalty Factors§ 82-4-1003
Through 82-4-1005 Reserved§ 82-4-1006
Abandoned Mine Reclamation Account§ 82-4-101
Short Title§ 82-4-102
Intent -- Findings -- Policy And Purpose§ 82-4-103
Definitions§ 82-4-104
Application§ 82-4-105
Through 82-4-110 Reserved§ 82-4-111
Repealed§ 82-4-112
Administration§ 82-4-113
Receipts Paid Into General Fund§ 82-4-114
Through 82-4-120 Reserved§ 82-4-121
Permit Required§ 82-4-122
Application And Approval Of PermitCite This Page — Counsel Stack
Bluebook (online)
Montana § 82-4-352, Counsel Stack Legal Research, https://law.counselstack.com/statute/mt/4/82-4-352.