82-4-229 . (Temporary) Minor revisions -- application -- exemptions.
(1)During the term of a permit, the permittee may apply to the department to revise the permit and reclamation plan. Major revisions are subject to the provisions of 82-4-225 .
(2)An application for a minor revision must:
(a)summarize proposed changes in sufficient detail for the department to determine that reclamation required under state and federal law will be accomplished;
(b)contain evidence that the changes in disturbed acres are insignificant in impact relative to the entire operation;
(c)identify previous environmental analyses relevant to the revision and demonstrate that the minor revision does not significantly change the human environment;
(d)document the adequacy of existing bonding; and
(e)include ev
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 82-4-229 (Minor Revisions -- Application -- Exemptions) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 1, Ch. 524, L. 2023.
Nearby Sections
15
§ 82-4-1001
Penalty Factors§ 82-4-1003
Through 82-4-1005 Reserved§ 82-4-1006
Abandoned Mine Reclamation Account§ 82-4-101
Short Title§ 82-4-102
Intent -- Findings -- Policy And Purpose§ 82-4-103
Definitions§ 82-4-104
Application§ 82-4-105
Through 82-4-110 Reserved§ 82-4-111
Repealed§ 82-4-112
Administration§ 82-4-113
Receipts Paid Into General Fund§ 82-4-114
Through 82-4-120 Reserved§ 82-4-121
Permit Required§ 82-4-122
Application And Approval Of Permit