§ 71-3-542 — Priority Of Construction Liens As Against Claims Other Than Construction Lien Claims

Montana § 71-3-542
JurisdictionMontana
Title 71MORTGAGES, PLEDGES, AND LIENS
Ch. 3LIENS
Part 5Construction Liens

This text of Montana § 71-3-542 (Priority Of Construction Liens As Against Claims Other Than Construction Lien Claims) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mont. Code Ann. § 71-3-542 (2026).

Text

71-3-542 . Priority of construction liens as against claims other than construction lien claims.

(1)A construction lien arising under this part has priority over any other interest, lien, mortgage, or encumbrance that may attach to the building, structure, or improvement or on the real property on which the building, structure, or improvement is located and that is filed after the construction lien attaches.
(2)An interest, lien, mortgage, or encumbrance that is filed before the construction lien attaches has priority over a construction lien arising under this part, except as provided in subsections (3) and (4).
(3)A construction lien has priority, to the extent of the value of the work or improvement that is severable, over an interest, lien, mortgage, or encumbrance that is filed bef

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 12, Ch. 202, L. 1987; amd. Sec. 2280, Ch. 56, L. 2009.