§ 18-2-417 — Wage Rate Adjustments For Multiyear Contracts
Montana § 18-2-417
JurisdictionMontana
Title 18PUBLIC CONTRACTS
Ch. 2CONSTRUCTION CONTRACTS
Part 4Special Conditions -- Standard Prevailing Rate of Wages
This text of Montana § 18-2-417 (Wage Rate Adjustments For Multiyear Contracts) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Mont. Code Ann. § 18-2-417 (2026).
Text
18-2-417 . Wage rate adjustments for multiyear contracts.
(1)Any public works contract that by the terms of the original contract calls for more than 30 months to fully perform must include a provision to adjust, as provided in subsection (2), the standard prevailing rate of wages to be paid to the workers performing the contract.
(2)The standard prevailing rate of wages paid to workers under a contract subject to this section must be adjusted 12 months after the date of the award of the public works contract. The amount of the adjustment must be a 3% increase. The adjustment must be made and applied every 12 months for the term of the contract.
(3)Any increase in the standard rate of prevailing wages for workers under this section is the sole responsibility of the contractor and any su
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
En. Sec. 5, Ch. 277, L. 2009.
Nearby Sections
15
§ 18-2-103
Supervision Of Construction Of Buildings§ 18-2-104
Scheduling Of State Building Program§ 18-2-106
Pecuniary Interest Prohibited§ 18-2-109
Exemption From Environmental Review§ 18-2-110
Reserved§ 18-2-114
Seal And Signature Of Architect On Plans§ 18-2-115
RepealedCite This Page — Counsel Stack
Bluebook (online)
Montana § 18-2-417, Counsel Stack Legal Research, https://law.counselstack.com/statute/mt/2/18-2-417.