§ 18-2-316 — Limit On Retainage For Public Contracts

Montana § 18-2-316
JurisdictionMontana
Title 18PUBLIC CONTRACTS
Ch. 2CONSTRUCTION CONTRACTS
Part 3Contract Requirements and Restrictions

This text of Montana § 18-2-316 (Limit On Retainage For Public Contracts) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mont. Code Ann. § 18-2-316 (2026).

Text

18-2-316 . Limit on retainage for public contracts.

(1)The maximum retainage applied to construction contracts administered by the state of Montana or any department, agency, or political subdivision of the state of Montana, by any county, municipality, or political subdivision of a county or municipality, or by a school district may not exceed 5% if the contractor is performing by the terms of the contract.
(2)The retainage percentage withheld by a government entity, as provided for in subsection (1), from a contractor is the maximum retainage percentage that a contractor may withhold from a subcontractor.
(3)For the purposes for this section, "retainage" means the ratio, in percent, of funds retained to the total amount to be paid to the contractor by the government entity.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 2, Ch. 222, L. 1999.