§ 18-2-312 — Excusable Delays

Montana § 18-2-312
JurisdictionMontana
Title 18PUBLIC CONTRACTS
Ch. 2CONSTRUCTION CONTRACTS
Part 3Contract Requirements and Restrictions

This text of Montana § 18-2-312 (Excusable Delays) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mont. Code Ann. § 18-2-312 (2026).

Text

18-2-312 . Excusable delays. A public contractor shall not be considered to be working beyond contract time if the delay is caused by an accident or casualty produced by physical cause which is not preventable by human foresight, i.e., any of the misadventures termed an "act of God".

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 2, Ch. 141, L. 1967; R.C.M. 1947, 82-1928.