§ 18-2-306 — Time Of Final Acceptance And Final Payment On Construction Contracts -- Interest
Montana·Title 18 PUBLIC CONTRACTS·Ch. 2 CONSTRUCTION CONTRACTS·Part 3 Contract Requirements and Restrictions
18-2-306 . Time of final acceptance and final payment on construction contracts -- interest.
(1)A government entity that enters into a contract for the construction of a building shall, unless otherwise provided by law or the contract and within 10 days after a request by the construction contractor for final acceptance, decide whether or not to make final acceptance. Within 30 days after final acceptance by the government entity, the government entity shall make the final payment of the contract price specified in the contract to the other party to the contract.
(2)Except as provided by law or the contract, a government entity that fails to complete the payment of the contract price at the time required by subsection (1) shall pay to the other party to the contract interest at the rate
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 18-2-306 (Time Of Final Acceptance And Final Payment On Construction Contracts -- Interest) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 1, Ch. 439, L. 1999; amd. Sec. 13, Ch. 181, L. 2001.
Nearby Sections
15
§ 18-2-103
Supervision Of Construction Of Buildings§ 18-2-104
Scheduling Of State Building Program§ 18-2-106
Pecuniary Interest Prohibited§ 18-2-109
Exemption From Environmental Review§ 18-2-110
Reserved§ 18-2-114
Seal And Signature Of Architect On Plans§ 18-2-115
Repealed