This text of Montana § 18-2-306 (Time Of Final Acceptance And Final Payment On Construction Contracts -- Interest) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mont. Code Ann. § 18-2-306 (2026).

Text

18-2-306 . Time of final acceptance and final payment on construction contracts -- interest.

(1)A government entity that enters into a contract for the construction of a building shall, unless otherwise provided by law or the contract and within 10 days after a request by the construction contractor for final acceptance, decide whether or not to make final acceptance. Within 30 days after final acceptance by the government entity, the government entity shall make the final payment of the contract price specified in the contract to the other party to the contract.
(2)Except as provided by law or the contract, a government entity that fails to complete the payment of the contract price at the time required by subsection (1) shall pay to the other party to the contract interest at the rate

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 1, Ch. 439, L. 1999; amd. Sec. 13, Ch. 181, L. 2001.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Montana § 18-2-306, Counsel Stack Legal Research, https://law.counselstack.com/statute/mt/2/18-2-306.