Montana Statutes

§ 18-2-303 — Construction Bids -- Minimum Requirements -- Effect Of Failure To Comply

Montana § 18-2-303
JurisdictionMontana
Title 18PUBLIC CONTRACTS
Ch. 2CONSTRUCTION CONTRACTS
Part 3Contract Requirements and Restrictions

This text of Montana § 18-2-303 (Construction Bids -- Minimum Requirements -- Effect Of Failure To Comply) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mont. Code Ann. § 18-2-303 (2026).

Text

18-2-303 . Construction bids -- minimum requirements -- effect of failure to comply.

(1)Each bid communicated to a state agency for the construction of a building must contain or be accompanied by the following items that may not be waived by the state agency:
(a)bid security, as required by 18-2-302 ;
(b)the unit price for each item required to be bid by unit price; and
(c)the signature, including an electronic signature allowed under 60-2-113 , of an individual authorized to submit the bid and authorized by that submission to agree to perform the contract if the bid is accepted. If the request for bid or other specifications provided by the state agency specify the individual required to submit the bid, the bid must comply with that requirement.
(2)The unit price must be expressly s

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 2, Ch. 282, L. 1999; amd. Sec. 1, Ch. 48, L. 2009.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Montana § 18-2-303, Counsel Stack Legal Research, https://law.counselstack.com/statute/mt/2/18-2-303.