18-2-303 . Construction bids -- minimum requirements -- effect of failure to comply.
(1)Each bid communicated to a state agency for the construction of a building must contain or be accompanied by the following items that may not be waived by the state agency:
(a)bid security, as required by 18-2-302 ;
(b)the unit price for each item required to be bid by unit price; and
(c)the signature, including an electronic signature allowed under 60-2-113 , of an individual authorized to submit the bid and authorized by that submission to agree to perform the contract if the bid is accepted. If the request for bid or other specifications provided by the state agency specify the individual required to submit the bid, the bid must comply with that requirement.
(2)The unit price must be expressly s
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 18-2-303 (Construction Bids -- Minimum Requirements -- Effect Of Failure To Comply) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 2, Ch. 282, L. 1999; amd. Sec. 1, Ch. 48, L. 2009.
Nearby Sections
15
§ 18-2-103
Supervision Of Construction Of Buildings§ 18-2-104
Scheduling Of State Building Program§ 18-2-106
Pecuniary Interest Prohibited§ 18-2-109
Exemption From Environmental Review§ 18-2-110
Reserved§ 18-2-114
Seal And Signature Of Architect On Plans§ 18-2-115
Repealed