This text of Montana § 18-1-402 (Administrative Procedures -- Exhaustion -- Time Limitations) is published on Counsel Stack Legal Research, covering Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mont. Code Ann. § 18-1-402 (2026).

Text

18-1-402 . Administrative procedures -- exhaustion -- time limitations. Whenever any contracting agency of the state of Montana provides a procedure for the settlement of any question or dispute arising between the contractor and the agency, the contractor, before proceeding to bring an action in court under the provisions of this part, shall resort to the procedure within the time specified in the contract or, if a time is not specified, within 90 days after the question or dispute has arisen, provided:

(1)in a case in which a settlement procedure is provided by the contracting agency, all actions authorized under this section must be commenced within 1 year after a final decision has been rendered pursuant to the settlement procedure; and
(2)in a case in which a settlement procedure is

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

En. Sec. 2, Ch. 138, L. 1955; R.C.M. 1947, 83-602; amd. Sec. 222, Ch. 56, L. 2009.