§ 85-15-212 — Operating Permit
Montana·Title 85 WATER USE·Ch. 15 DAM SAFETY ACT·Part 2 Construction, Inspection, and Repair of Dams
85-15-212 . Operating permit.
(1)An operation plan must be prepared by the owner and approved by the department prior to operation of the high-hazard dam or reservoir. The operation plan must set forth at a minimum:
(a)a reservoir operation procedure;
(b)a maintenance procedure for the high-hazard dam and appurtenant works; and
(c)emergency procedures and warning plans.
(2)When construction is complete and if the high-hazard dam or reservoir conforms to the construction permit and when an operation plan has been approved, the department shall issue a permit to operate the high-hazard dam or reservoir, containing conditions on the safe operation of the high-hazard dam as it considers necessary.
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 85-15-212 (Operating Permit) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 9, Ch. 501, L. 1985; amd. Sec. 5, Ch. 418, L. 1993.
Nearby Sections
15
§ 85-15-101
Renumbered 85-15-207§ 85-15-102
Renumbered 85-15-208§ 85-15-103
Repealed§ 85-15-104
Renumbered 85-15-107§ 85-15-105
Short Title§ 85-15-106
Definitions§ 85-15-107
Exemptions§ 85-15-108
Entry Upon Land§ 85-15-109
Legal Assistance§ 85-15-110
Rules§ 85-15-111
Through 85-15-114 Reserved§ 85-15-115
Purpose§ 85-15-201
Renumbered 85-15-306§ 85-15-202
Renumbered 85-15-307§ 85-15-203
Renumbered 85-15-308