§ 85-15-210 — Preparation And Approval Of Plans
Montana·Title 85 WATER USE·Ch. 15 DAM SAFETY ACT·Part 2 Construction, Inspection, and Repair of Dams
85-15-210 . Preparation and approval of plans.
(1)A person may not begin construction of a high-hazard dam as determined under 85-15-209 without first obtaining a construction permit from the department.
(2)An application for a construction permit must be submitted to the department and must contain:
(a)plans and specifications for the proposed construction, prepared by or under the direction of an engineer experienced in dam design and construction; and
(b)other data and information required by the department.
(3)Within 60 calendar days after receipt of the application and any additional information requested by the department, the department shall:
(a)issue a construction permit or deny the application, as filed; or
(b)issue a construction permit upon terms, conditions, or modific
Free access — add to your briefcase to read the full text and ask questions with AI
Montana § 85-15-210 (Preparation And Approval Of Plans) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
En. Sec. 7, Ch. 501, L. 1985.
Nearby Sections
15
§ 85-15-101
Renumbered 85-15-207§ 85-15-102
Renumbered 85-15-208§ 85-15-103
Repealed§ 85-15-104
Renumbered 85-15-107§ 85-15-105
Short Title§ 85-15-106
Definitions§ 85-15-107
Exemptions§ 85-15-108
Entry Upon Land§ 85-15-109
Legal Assistance§ 85-15-110
Rules§ 85-15-111
Through 85-15-114 Reserved§ 85-15-115
Purpose§ 85-15-201
Renumbered 85-15-306§ 85-15-202
Renumbered 85-15-307§ 85-15-203
Renumbered 85-15-308