85-1-514 . Power generation negotiation process.
(1)A person with federal authorization or, if authorization is not required, a person planning to construct a small-scale hydroelectric generation facility at a state-owned project shall submit an application to the department for hydroelectric development at the state-owned project site.
(2)Upon receipt of a written application under subsection (1), the department shall make an investigation and prepare a report on the value of the power site, the plans of development submitted by the applicant, and any other matters relating to the proposed development that the department considers necessary for the proper development of hydroelectric generation at the state-owned project.
(3)Upon completion of the report, the department may negotiate w
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
En. Sec. 3, Ch. 293, L. 1985; amd. Sec. 439, Ch. 418, L. 1995.
Nearby Sections
15
§ 85-1-101
Policy Considerations§ 85-1-102
Definitions§ 85-1-103
Interpretation Of Title§ 85-1-104
Through 85-1-110 Reserved§ 85-1-111
Public Ways§ 85-1-112
Navigable Waters§ 85-1-113
Through 85-1-120 Reserved§ 85-1-121
Repealed§ 85-1-122
Clark Fork River§ 85-1-201
Rules§ 85-1-202
Repealed§ 85-1-203
State Water Plan§ 85-1-204
Department Powers Over State Water§ 85-1-206
Construction Of Works By DepartmentCite This Page — Counsel Stack
Bluebook (online)
Montana § 85-1-514, Counsel Stack Legal Research, https://law.counselstack.com/statute/mt/1/85-1-514.