§ 444.875 — Release of all or part of performance bond, procedure — objections may be filed.

Missouri § 444.875
JurisdictionMissouri
Title XXIXOWNERSHIP AND CONVEYANCE OF PROPERTY
Ch. 444Rights and Duties of Miners and Mine Owners

This text of Missouri § 444.875 (Release of all or part of performance bond, procedure — objections may be filed.) is published on Counsel Stack Legal Research, covering Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mo. Rev. Stat. § 444.875 (2026).

Text

1.The permittee may file a request with the commission for the release of all or part of a performance bond or deposit.  Within thirty days after any application for bond release has been filed, the operator shall submit a copy of an advertisement placed at least once a week for four successive weeks in a newspaper of general circulation in the locality of the surface coal mining operation.  Such advertisement shall be considered part of any bond release application and shall contain a notification of the precise location of the land affected, the number of acres, the permit and the date approved, the amount of the bond filed and the portion sought to be released, and the type and appropriate dates of reclamation work performed, and a description of the results achieved as they relate to

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(L. 1979 H.B. 459, A.L. 1993 H.B. 312 & 257)