§ 227.555 — Relocation plan, contents — review of plan — meeting for coordination of work required — notification of approval of plan.

Missouri § 227.555
JurisdictionMissouri
Title XIVROADS AND WATERWAYS
Ch. 227State Highway System

This text of Missouri § 227.555 (Relocation plan, contents — review of plan — meeting for coordination of work required — notification of approval of plan.) is published on Counsel Stack Legal Research, covering Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mo. Rev. Stat. § 227.555 (2026).

Text

1.Within one hundred twenty days of receiving written notice of approval of the utility plan of adjustment from the commission, the owner shall provide the commission with a relocation plan.  The one hundred twenty-day clock stops after the relocation plan is submitted by the owner.  If, after timely submission of the relocation plan by the owner, revisions or alterations are necessary for any reason, or if the original relocation plan was incomplete due to information needed from other parties, the one hundred twenty-day clock begins to run again when the needed information is received back by the owner.
2.The relocation plan shall include a narrative description of work that will be done in relocating the owner's utility facilities and whether the work or a portion of the work must

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(L. 2005 H.B. 209 § 227.245) Effective 1-01-06

Nearby Sections

15
§ 227.010
Definitions.
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Missouri § 227.555, Counsel Stack Legal Research, https://law.counselstack.com/statute/mo/227/227.555.