§ 5 §1747 — Questionnaire as prebid qualification

Maine·Title 5 ADMINISTRATIVE PROCEDURES AND SERVICES·Part 4 FINANCE·Ch. 153 PUBLIC IMPROVEMENTS

The public official may require, from a firm proposing to bid on public work duly advertised, a standard qualification statement and a letter from a licensed bonding company confirming that the firm has the financial capacity to perform the work before furnishing that person with plans and specifications for the proposed public work advertised. The Director of General Services, after consultation with the appropriate department head or superintendent of schools, may refuse to release plans and specifications to a contractor for the purpose of bidding on a project:

1.Untimely completion. If, in the opinion of the director, there is evidence the contractor has not completed in a timely manner a prior construction project or projects and the resulting noncompletion clearly reflects disregard

Free access — add to your briefcase to read the full text and ask questions with AI

Maine § 5 §1747 (Questionnaire as prebid qualification) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

PL 1989, c. 483, §A20 (RPR). PL 1993, c. 324, §1 (AMD). PL 1997, c. 295, §1 (AMD). PL 2001, c. 271, §§2-5 (AMD). PL 2003, c. 589, §1 (AMD).