1.General permit.
A general permit is required for the alteration of a freshwater, nontidal stream to construct an agricultural irrigation pond. If the provisions of this section are met, an individual permit is not required.
2.Eligibility criteria.
The following eligibility criteria must be met.
3.Standards.
The following standards must be met.
4.Submissions.
The following provisions apply to the submission of applications.
5.Review period.
Work may not commence until 30 days after the department has accepted an application for processing. This period may be extended pursuant to section 344‑B with the consent of the applicant.
6.Notification.
The department shall notify the applicant in writing within 30 days of acceptance for processing if the department determines that the require
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
PL 1995, c. 659, §1 (NEW). PL 1999, c. 243, §§15,16 (AMD). PL 1999, c. 556, §33 (AMD). PL 2007, c. 649, §10 (AMD). PL 2011, c. 538, §§10, 11 (AMD).
Nearby Sections
15
§ 38 §480-A
Findings; purpose; short title§ 38 §480-AA
Coastal sand dune rules§ 38 §480-B
Definitions§ 38 §480-C
Prohibitions§ 38 §480-D
Standards§ 38 §480-E
Permit processing requirementsCite This Page — Counsel Stack
Bluebook (online)
Maine § 38 §480-Y, Counsel Stack Legal Research, https://law.counselstack.com/statute/me/38%20%C2%A7480-Y.