§ 35-A §4707 — Stranded costs; notice of risk

Maine·Title 35-A PUBLIC UTILITIES·Part 4 GAS·Ch. 47 GAS UTILITIES
Notwithstanding any other provision of this Title, costs arising from obligations incurred by a gas utility after March 1, 1998, other than costs or obligations that are beyond the control of the gas utility, determined by the commission in an adjudicatory proceeding to be unrecoverable as a result of competition or deregulation are incurred at the risk of the shareholders of the gas utility and may not be borne by ratepayers of the gas utility. This section may not be interpreted as requiring that costs incurred prior to March 1, 1998 be recovered from ratepayers.

Free access — add to your briefcase to read the full text and ask questions with AI

Maine § 35-A §4707 (Stranded costs; notice of risk) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

PL 1997, c. 707, §10 (NEW).