Text

At least 30 days before beginning construction of an interstate natural gas pipeline within this State, the corporation shall file with the Secretary of State a certified copy of the certificate of public convenience and necessity issued to it under the Federal Natural Gas Act or, if the pipeline is intrastate, a certificate exhibiting the commission's authorization.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

PL 1987, c. 141, §A6 (NEW).

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Maine § 35-A §4503, Counsel Stack Legal Research, https://law.counselstack.com/statute/me/35-A%20%C2%A74503.