§ 35-A §3610 — Project deadline; completion deadline

Maine·Title 35-A PUBLIC UTILITIES·Part 3 ELECTRIC POWER·Ch. 36 COMMUNITY-BASED RENEWABLE ENERGY
The commission may not issue an order after December 31, 2015 directing an investor-owned transmission and distribution utility to enter into a long-term contract under this chapter nor allow a consumer-owned transmission and distribution utility to enter into a long-term contract under this chapter. All community-based renewable energy projects that have been selected for a long-term contract must become operational and commence generating electricity by December 31, 2018.

Free access — add to your briefcase to read the full text and ask questions with AI

Maine § 35-A §3610 (Project deadline; completion deadline) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

PL 2015, c. 232, §4 (NEW).